Assessment

Leave the Paris data centre. Start with 64 servers.

Current state, target state, the cost comparison, the risks and the next steps.

Cloud programme Steering committee · Q4

Current state

From 412 servers to a first wave of 64

Paris data centre.

  1. Inventory 412 Every server in the CMDB export
  2. In use 318 −94 idle for 90 days: decommission
  3. Supported OS 241 −77 on end-of-life systems: upgrade first
  4. First wave 64 Stateless tiers with a named owner

Source: CMDB export and 90-day utilisation report

Data centre exit / assessment02 / 09

Current cost

Hardware and licences are two thirds of the bill

Annual run cost of the data centre.

  • Hardware and support410 k€39%
  • Licences290 k€28%
  • Facilities and power180 k€17%
  • Operations staff120 k€11%
  • Network50 k€4.8%
Hardware and licences are two thirds of the bill
Hardware and support410 k€39%
Licences290 k€28%
Facilities and power180 k€17%
Operations staff120 k€11%
Network50 k€4.8%

Source: finance cost centre 4410, FY2026

Data centre exit / assessment03 / 09

Cost by workload

Three workloads hold 90% of the spend

Monthly cost in k€.

Three workloads hold 90% of the spend
WorkloadComputeStorageNetworkLicences
Customer portal18.43.11.24
Data platform12.99.60.86.5
Integration hub7.20.92.41.5
Internal tools2.80.60.20
Batch jobs2.11.40.10
Total43.415.64.712

Source: cost allocation model v3

Data centre exit / assessment04 / 09

Target state

Managed services cut the run cost by 35%

Monthly run cost in k€, after wave 3.

  • Compute42 → 24
  • Databases18 → 15
  • Storage14 → 11
  • Operations12 → 6
Managed services cut the run cost by 35%
TodayTarget
Compute42 k€24 k€
Databases18 k€15 k€
Storage14 k€11 k€
Operations12 k€6 k€
Total86 k€56 k€

Source: cloud pricing calculator, list prices

Data centre exit / assessment05 / 09

Risks

Four risks, one needs a decision today

Reviewed with service owners.

Four risks, one needs a decision today
RiskImpactLikelihoodOwnerMitigation
Data loss during the database cut-overCriticalLowDBA teamRehearse twice; keep the source read-only for 48 h.
Licence costs double on the new platformHighMediumProcurementNegotiate before the pilot ends.
Team lacks cloud operations experienceMediumHighPlatform leadPair with the vendor for the first three waves.
Data centre contract renews in JuneHighLowProgramme leadGive notice now for a 12-month exit.
Data centre exit / assessment06 / 09

Next steps

Three waves, out by next autumn

Plan for approval.

  1. Oct

    Landing zone

    Network, identity and guardrails in place.

  2. Nov

    Wave 1

    64 stateless servers.

  3. Feb

    Wave 2

    Databases and the data platform.

  4. May

    Wave 3

    Integration hub and batch jobs.

  5. Sep

    Exit

    Hardware returned and contract closed.

Data centre exit / assessment07 / 09

Decisions

Three decisions for this committee

Needed to start wave 1 in November.

Three decisions for this committee
DoneOwnerDue
Approve the wave 1 scope of 64 serversSteering committeeToday
Give notice on the data centre contractProcurement31 Oct
Fund the landing zone and vendor pairingFinance31 Oct
Data centre exit / assessment08 / 09

Sources

  1. 02From 412 servers to a first wave of 64CMDB export, 1 September
  2. Utilisation report, 90 days
  3. 03Hardware and licences are two thirds of the billFinance cost centre 4410, FY2026
  4. 04Three workloads hold 90% of the spendCost allocation model v3
  5. 05Managed services cut the run cost by 35%Cloud pricing calculator